Company
Logo
Disaster Recovery Plan
<Company Name>
<Company Site Addr1
Site Addr2
Site Addr3
Site Addr4
Postcode>
Issued by:
|
<Plan Owner>
|
Version:
|
|
Date:
|
|
Copy
Number:
|
|
<Company Name> Confidential
Instructions for Using This Template
This template Disaster Recovery Plan is a typical example of
the contents of a plan document, which will help you save time when
writing your own. However, ALL of this plan is designed to be CUSTOMIZED
for the solution designed specifically for your company. In particular,
the teams, timescales and responsibilities are for example ONLY and are
not necessarily recommendations. Note also that some of the teams
referred to may be only one person.
The layout has been designed to be easy to navigate, but,
again, you may wish to modify it, particularly the cover page, to suit a
house style.
The document contains some hints for writing your own plan;
these are in bold italic text. Remember to delete these paragraphs,
together with these instructions, when you finalize your
plan.
When you have written your plan, remember to:
-
Customize the footer in the first two sections (Header and
Footer on the View menu).
-
Search for < to ensure that you have entered appropriate
text in all placeholders.
-
Regenerate the table of contents and the cross references
(Select All with Ctrl A and press F9).
Version 1.2 May 2001
Table of
Contents
Plan Revision
History
It is important that this Disaster recovery Plan accurately reflects
the current situation and business requirements at <Company Name>.
Updates must be provided to <Plan Owner>
The following table describes the history of this document.
-
Version
|
Date Issued
|
Reason for Update
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1.About This
Disaster Recovery Plan
Hint:
Clearly define the scope of the plan. For example, the plan may cover
the company’s computer processing only, or it may be broader and
extend to environmental and safety issues.
1.1.Purpose and Scope of This Plan
This plan has been designed and written to be used in the event of a
disaster affecting <Company name> at <Company Site Address>.
This plan is structured around teams, with each team having a set of
specific responsibilities.
The decision to initiate disaster recovery procedures will be taken
by the Disaster Management Team Leader or his deputy after
assessing the situation following a disaster or crisis.
If the Disaster Management Team Leader decides to initiate
disaster recovery procedures, then all members of the recovery teams
will follow the procedures contained in this plan until recovery is
complete.
This plan contains all the information necessary to restore an
operational service in the event of a serious disruption of computer
services at <Company Site>. 1.2.Updating This Plan
This plan must be kept up to date.
It is the responsibility of <Plan Owner> to ensure that
procedures are in place to keep this plan up to date. If,
whilst using the plan, you find any information which is incorrect,
missing or if you have a problem in understanding any part of this plan
please inform <Plan Owner> so that it may be corrected. It is
important that everyone understands their role as described in this
plan.
Updated versions of the plan are distributed to the authorised
recipients, listed in Section 1.3, Distribution List.
1.3.Distribution List
<Plan Owner> is responsible for distributing this plan. Each
plan holder, listed in the table below, receives two copies of this
plan. One copy is to be kept at the place of work and the other copy
at home or other safe offsite location. These copies have an official
copy number.
Each team leader must ensure that each team member has two copies of
the plan.
-
Name
|
Copy Number
|
<Disaster
Management Team Leader>
|
|
<Operations
Team Leader>
|
|
<Network
Team Leader>
|
|
<Facilities
Team Leader>
|
|
|
|
|
|
|
|
|
|
|
|
Offsite Copy 1
|
|
Offsite Copy 2
|
|
2.Plan Objectives
A disaster is defined as an incident which results in the loss of
computer processing at the <Company Name> site at
<Location>, to the extent that relocation to a Standby Facility
must be considered. A disaster can result from a number of accidental,
malicious or environmental events such as fire, flood, terrorist attack,
human error, software or hardware failures.
The primary objective of this Disaster recovery Plan is to ensure the
continued operation of identified business critical systems in the event
of a disaster.
Specific goals of the plan are :
-
To be
operational at the standby facility within <X> working days of
a standby invocation
-
To operate
at the standby facility for up to <DEFINED PERIOD OF TIME>
-
To
reinstate <Company Name> facilities in the <Company Name>
premises within the maximum working standby period
-
To minimize
the disruption to <Company Name>’ s business
3.Recovery Teams and Responsibilities
Hint: The recovery teams defined for a company vary according
to the specific needs of that company. Adapt this section to
describe the recovery teams applicable for your situation.
This section defines the functional responsibilities of each
recovery team.
The names of all the team members are to listed in Section 12.2, Recovery Team Members.
3.1.Disaster Management Team
The Disaster Management Team is responsible for providing overall
direction of the data centre recovery operations. It ascertains the
extent of the damage, activates the recovery organisation and
notifies the team leaders. Its prime role is to monitor and direct
the recovery effort. It has a dual structure in that its members
include Team Leaders of other teams.
The Disaster Management Team Leader is responsible for
deciding whether or not the situation warrants the introduction of
disaster recovery procedures. If he decides that it does, then the
organisation defined in this section comes into force and, for the
duration of the disaster, supersedes any current management
structures.
The Disaster Management Team operates from the Command Centre.
3.1.1.Disaster Management Team Charter
The Disaster Management Team is responsible for the following:
-
Making decisions about restoring the computer processing
environment in order to provide the identified level of operational
service to users.
-
Managing all the recovery teams and liaising with <Company
Name>‘s management, company headquarters and users, as
appropriate.
-
Maintaining audit and security control during the recovery from
disaster.
-
Controlling and recording emergency costs and expenditure.
3.1.2.Responsibilities
-
Evaluating the extent of the problem and potential consequences.
-
Notifying senior management of the disaster, recovery progress and
problems.
-
Initiating disaster recovery procedures.
-
Co ordinating recovery operations
-
Monitoring recovery operations and ensuring that the schedule is
met.
-
Documenting recovery operations.
-
Liaising with user management.
-
Expediting authorisation of expenditures by other teams.
-
Recording emergency extraordinary costs and expenditure
-
Making a detailed accounting of the damage to aid in insurance
claims.
-
Ensuring that the conversion to the standby facilities and the
final resumption of operations at the data centre are under
sufficient audit control to provide reliability and consistency to
the accounting records.
-
Monitoring computer security standards.
-
Ensuring that appropriate arrangements are made to restore the site
and return to the status quo within the time limits allowed for
emergency mode processing.
-
Approving the results of audit tests on the applications which are
processed at the standby facility shortly after they have been
produced.
-
Performing a detailed audit review of the critical accounting files
after the first back up cycle has been completed.
-
Declaring that the Disaster recovery Plan is no longer in effect
when computer processing is restored at the primary site.
3.2.Operations Team
The Operations Team is responsible for the computer environment
(computer room and other vital computer locations) and for
performing tasks within those environments.
This team is responsible for restoring computer processing and for
performing computer room activities.
3.2.1.Operations Team Charter
The Operations Team is responsible for the following:
-
Ensuring that the standby equipment meets the recovery schedules.
-
Installing the computer hardware and setting up the latest version
of the operating system at the standby facility. (This may be done
together with the Standby Vendor team.)
-
Obtaining all appropriate historical/current data from the vault
location and restoring an up to date application systems
environment.
-
Providing the appropriate management and staffing of the standby
computer processing centre, data control, help desk and media
control/tape library in order to meet the defined level of user
requirements.
-
Support operable versions of all critical applications needed to
satisfy the minimum operating requirements.
-
Performing backup activities at the standby site.
3.2.2.Responsibilities
-
Providing on going technical support at the standby facility.
-
Working with the Networks Team to restore local and wide area data
communications services to meet the minimum processing
requirements.
-
Obtaining all necessary back ups from off site storage.
-
Initiating operations at the standby facility.
-
Re establishing software libraries and databases to the last
backup.
-
Co-ordinating the user groups to aid the recovery of any
non recoverable (i.e. not available on the latest MT dump)
data
-
Providing sufficient personnel to support operations at the standby
facility
-
Re establishing the Help Desk, Data Control and Media
Control/Tape Library functions at the standby facilities.
-
Managing the standby facilities to meet users' requirements
-
Establishing processing schedule and inform user contacts
-
Arranging for acquisition and/or availability of necessary computer
supplies
-
Ensuring that all documentation for standards, operations, vital
records maintenance, application programs etc. are stored in a
secure/safe environment and reassembled at the standby facilities,
as appropriate.
3.3.Networks Team
The networks team is responsible for all computer networking and
communications.
3.3.1.Networks Team Charter
The Networks Team is responsible for the following:
-
Arranging new local and wide area data communications facilities
and a communications network, which links the standby facility to
the critical users
-
Installing a minimum voice network to enable identified critical
telephone users to link to the public network.
3.3.2.Responsibilities
-
Evaluate the extent of damage to the voice and data network and
discuss alternate communications arrangements with telecoms service
providers.
-
Establish the network at the standby facilities in order to bring
up the required operations.
-
Define the priorities for restoring the network in the user areas.
-
Order the voice/data communications and equipment as required.
-
Supervise the line and equipment installation for the new network.
-
Providing necessary network documentation.
-
Providing ongoing support of the networks at the standby facility.
-
Re establish the networks at the primary site when the post
disaster restoration is complete.
3.4.Facilities Team
The Facilities Team is responsible for the general environment
including buildings, services and all environmental issues outside
of the computer rooms.
This team has responsibility for security, health and safety and for
replacement building facilities.
3.4.1.Facilities Team Charter
-
Administering the reconstruction of the original site for recovery
and operation
-
Arranging all transport to the standby facility.
-
Controlling security at the standby facility and the damaged site.
(Note: physical security may need to be increased.)
3.4.2.Responsibilities
-
In conjunction with the Disaster Management Team, evaluating the
damage and identifying equipment which can be salvaged.
-
Working with the Networking Team to have lines ready for rapid
activation.
-
As soon as the standby site is occupied, cleaning up the disaster
site and securing that site to prevent further damage.
-
Supplying information for initiating insurance claims.
-
Ensuring that insurance arrangements are appropriate for the
prevailing circumstances (i.e. any replacement equipment is
immediately covered etc.)
-
Preparing the original data centre for re occupation.
-
Maintaining current configuration schematics of the Data Centre
(stored off site) This should include:
-
Controlling security within the disaster area.
-
Arranging for all necessary office support services.
-
Dealing with staff safety and welfare.
3.5.Communications Team
3.5.1.Communications Team Charter
The Communications Team is responsible for obtaining communications
directives from the Disaster Management Team, and communicating
information during the disaster and restoration phases to employees,
suppliers, customers and the media (Press, TV, radio).
3.5.2.Responsibilities
-
Liaising with the Disaster Management Team to obtain directives on
the messages to communicate.
-
Making statements to local, national and international media, as
appropriate.
-
Informing suppliers and customers of any potential delays.
-
Informing employees of the recovery progress of the schedules.
-
Ensuring that there is no mis-communications that could damage the
image of the company.
-
Any other public relations.
3.6.<Other Recovery Teams>
Hint: Include a section on any other teams that are defined in
the company’s disaster recovery plans. Ensure that you describe
each team’s responsibilities and activities.
Other recovery teams may include the following:
3.6.1.<Other Recovery Team> Charter
3.6.2.Responsibilities
3.7.Standby Facilities Team
Hint: Include the responsibilities of the Standby Facilities
team. This team may be composed, wholly or in part, of personnel
from a vendor providing the standby facility.
3.7.1.Standby Facilities Team Charter
3.7.2.Responsibilities
4.What To Do in the Event of a Disaster
Hint: you may wish to include your Company standard
Fire/Evacuation/Safety procedures in an Appendix or as the main text
for 4.1 below.
The most critical and complex part of the management of resources is
in the planning and organisation of the required personnel during
the invocation of the plan.
Personnel must be well-rehearsed, familiar with the Disaster
recovery Plan and be sure of their assignments.
4.1.Standard Emergency Procedures
The first priority in a disaster situation is to ensure safe
evacuation of all personnel.
In the event of a major physical disruption, standard emergency
procedures must be followed. This means immediately:
-
Activating the standard alarm procedures for that section of the
building to ensure that Medical, Security and Safety departments
and emergency authorities are correctly alerted.
-
If necessary, evacuating the premises following the laid down
evacuation procedures and assemble outside at the designated
location, if it is safe to do so.
4.2.The First Steps for the Recovery Teams
-
The Facilities Team assesses the nature and extent of the problem.
-
If it is safe to do so, the Operations Team switches off all
equipment in the computer room, including air conditioners.
-
Building Security alerts the Disaster Management Team Leader.
-
The Facilities Team give an initial assessment to the Disaster
Management Team Leader, who needs to know the extent of the
damage to the buildings and equipment and the staff status. Also
report what actions have been taken.
4.3.The Next Steps
The Disaster Management Team Leader decides whether to
activate the Disaster recovery Plan, and which recovery scenario
will be followed.
The recovery teams then follow the defined recovery activities and
act within the responsibilities of each team, as defined in this
Disaster recovery Plan.
5.Recovery Scenarios
Hint: this section optionally provides the opportunity to
specify actions which may be taken if the 'disaster' is less than
total. Such a situation may prevail on a large site with multiple
buildings - perhaps even with multiple computer rooms in different
locations. Clearly, this will be inappropriate in some cases.
Remember, the action plans are by way of example only and are not
intended to suggest or recommend what you should do.
This section describes the various recovery scenarios that can be
implemented, depending on the nature of the disaster and the extent
of the damage. The Disaster Management Team Leader decides
which recovery scenario to implement when he or she activates the
Disaster recovery Plan.
5.1.Scenario One: Minor Damage
In this scenario, only a part of the computer processing environment
is out of action, but the communication lines and network are still
up and running. The goal of the recovery process in this case is to
move the applications from the systems which are unavailable to the
Standby Facility.
In this scenario the building is still available and the users can
use normal office space to wait for the restart of computer
processing.
5.1.1.Action Plan
-
Task
|
Team
|
Evaluate the
damage
|
Disaster
Management Facilities and Operations
|
Identify the
concerned applications
|
Disaster
Management and Operations
|
Request the
appropriate resources at the Standby Facility
|
Disaster
Management
|
Obtain the
appropriate backups
|
Operations
|
Restart the
appropriate applications at the Standby Facility
|
Operations
|
Inform users of
the new procedures
|
Communications
|
Order
replacement equipment to replace the damaged computers.
|
Operations
|
Install
replacement equipment and restart the applications
|
Operations
|
Inform users of
normal operations
|
Communications
|
5.2.Scenario Two: Major Damage
In this scenario, the entire computer processing environment (or
most of it) is out of action. Communication lines and the network
are out of action.
The goal of the recovery process in this scenario is to move all
identified applications to the Standby Facility.
This scenario requires a full recovery procedure, as documented in
this Disaster recovery Plan.
6.Recovery Activities
This section contains a list of tasks for each of the recovery
teams. Sensible judgement must be exercised to determine what
activities are appropriate based on the nature and extent of the
disruption.
Hint: the timescales used here are for example only and should
be modified to suit your Organisation. For example, some production
process may require a significant action to be taken every two
hours, or there may be something which repeats on a twelve-hour
cycle. Modify the timescales and actions to reflect these
requirements.
6.1.Overview of the Tasks for Each Team
The following table provides an overview of the main
responsibilities of each recovery team during the lifecycle of the
disaster recovery process. The detailed tasks for each team are
listed in the following sections.
Phase
Team
|
|
Site in normal working conditions
|
|
Decision to Activate the Plan
|
Plan is in Operation (Standby Facility)
|
Return to the Primary Site
|
|
|
|
|
|
|
|
|
|
Disaster
|
|
Test the Plan
|
D
|
Evaluate damage
|
Make decisions
|
|
Management
|
|
Update the Plan
|
I
|
Ensure safety
|
Co-ordinate activities
|
|
team
|
|
|
S
|
Call team meeting
|
Inform senior management
|
|
|
|
|
A
|
|
|
|
|
|
|
Test the Plan
|
S
|
Assess damage
|
Salvage operations
|
|
|
Facilities
|
|
|
T
|
Attend team meeting
|
Security
|
|
team
|
|
|
E
|
|
Administration services
|
|
|
|
|
R
|
Prepare/move to S'by Facility
|
Supervise repairs and prepare for
|
Supervise re-occupation of Primary
|
|
|
|
|
|
|
return to Primary Site
|
Site or move to new permanent site
|
|
|
|
|
O
|
|
|
|
|
Operations
|
|
Test the Plan
|
C
|
Attend team meeting
|
Move to Standby Facility
|
Reinstate computer processing
|
|
team
|
|
|
C
|
Prepare move to Standby Facility
|
Operate the Standby Facility
|
|
|
|
|
|
U
|
|
|
|
|
Networks
|
|
Test the Plan
|
R
|
Attend team meeting
|
Move to Standby Facility
|
Reinstate network communications
|
|
team
|
|
|
S
|
Prepare/move to S'by Facility
|
Operate the Standby Facility
|
|
|
|
|
|
|
|
|
|
|
|
|
Test the Plan
|
|
Attend team meeting
|
Operate 'Crisis Desk' to: Inform suppliers
|
|
Communications
|
|
|
|
Set up 'Crisis Desk'
|
Inform customers
|
|
team
|
|
|
|
|
Inform employees
|
|
|
|
|
|
|
Inform the Press
|
|
|
|
|
|
|
Be the public relations contact generally
|
|
6.2.Disaster Management Team Tasks
6.2.1.Immediate
-
Receive an initial assessment of the nature and extent of the
problem.
-
Decide whether to activate the Plan.
-
Alert all Recovery team leaders.
-
Alert and mobilize all other team members.
-
Make a preliminary (verbal) report to senior management.
-
Call an initial meeting of the recovery team leaders with the
following objectives:
-
To define
the problem, the extent of the disruption, its consequences and the
probable implications for the foreseeable future.
-
To set up a
specified location as a Control Centre.
-
To agree
each team's objectives for the next three hours.
-
To set up a
second meeting for three hours later.
-
Make a second, more detailed, report to senior management on the
content of the meeting and the actions being taken.
6.2.2.Within Three Hours
-
Call a second meeting of the recovery team leaders with the
following objectives:
-
To receive
initial reports from the recovery team leaders.
-
To take the
decision to implement disaster recovery procedures.
-
To agree
each team's objectives for the next twenty four hours.
-
To set up a
third meeting for twenty four hours later.
6.2.3.Within Twenty Four Hours
-
Contact the supplier of the standby facilities to invoke the
installation as per contract.
-
Agree installation schedule with the supplier of the standby
facility.
-
Prepare plans for the transition to the standby facility.
-
Make official declarations (for example, place of work change to any
regulatory authorities).
-
Report progress to senior management.
6.2.4.Ongoing
-
Act as the main point of contact with the emergency services
(Police, Fire, Ambulance).
-
Monitor on a regular basis all activities to exercise and maintain
control over delivery and installation dates.
-
Document progress against agreed schedules.
6.3.Operations Team Tasks
6.3.1.Immediate
-
Attend the initial meeting called for recovery team leaders.
-
Alert and mobilize all other team members.
6.3.2.Within Three Hours
-
Contact all operations, data preparation, data control and
microfiche staff.
-
Inform all staff of the problem and the actions being taken
-
Ensure all staff remain calm and understand their roles.
-
Inform all staff of any temporary instructions.
-
Inform all user contacts of the nature and extent of the problem.
telling them that they will be kept informed of the plans to
recover.
-
Report back at the second meeting of recovery team leaders.
6.3.3.Within Twenty Four Hours
-
Contact suppliers of:
-
hardware
-
communications equipment
-
ancillary equipment.
-
Inform them of the arrangements for moving to the standby
facilities.
-
Order new equipment and arrange to have it installed in the standby
facility.
-
Initiate 'interim' back up procedures for priority systems
(this may involve manual procedures)
-
Brief all operations staff required to travel to the interim
site(s).
6.3.4.Ongoing
-
Call all user contacts on a regular basis, advising them of the
disruption and the actions being taken.
-
In conjunction with the Facilities Team, monitor the delivery and
installation of new/replacement hardware, communications and
ancillary equipment.
-
In the light of the disruption, review all production schedules in
terms of jobs to be run, timings, priorities and dependencies.
-
Prepare production schedules in readiness for start up at the
standby site.
-
Accept hand over of standby site from the Facilities Team.
-
In conjunction with the Networks Team, initialise and test the
systems:
-
hardware
-
operating systems
-
communications network
-
Before undertaking any processing, take security copies of all files
and programs.
-
Transfer security copies to off site storage location.
-
Start processing in accordance with prepared production schedules.
-
Discontinue work at any interim site(s).
6.4.Networks Team Tasks
6.4.1.Immediate
-
Alert and mobilize all other team members.
-
Attend the initial meeting called for recovery team leaders.
6.4.2.Within Three Hours
-
Contact relevant staff with a networks responsibility, inform them
of the problem and the actions being taken.
-
Ensure that all staff remain calm and understand their roles.
-
Inform networks staff of any temporary instructions.
-
Help to compile an inventory of surviving communications equipment
(voice/data) and that to be acquired.
-
Ensure that all relevant documentation is at hand or retrieved from
the off site storage facility, for the reinstatement of the
network.
-
Liaise with the Operations Team as to the status of communications
equipment and assist with acquiring replacement equipment if
required.
-
Provide further information to enable the Communications Team to
keep users informed of current position if required.
-
Ensure that all documentation/ information is available for the
Operations and Facilities teams in order to connect the voice, local
and wide area network to the standby facility.
-
Liaise with the Standby Facility and telecom service providers to
monitor progress of communications reinstatement.
-
Report back at the second meeting of recovery team leaders.
6.4.3.Within Twenty Four Hours
-
Define the priorities for restoring the network on a gradual basis
in order to provide a minimum initial communications requirement for
normal operations.
-
Liaise with suppliers of communications equipment to ensure prompt
delivery, if required.
-
In conjunction with the Operations Team, ensure that the reinstated
communications network is operable and tested.
-
Provide ongoing support for the communications network and carry out
any re configuration of the reinstated network that may be
necessary.
-
Attend the third meeting of the disaster recovery team leaders and
report the restoration status.
6.4.4.Ongoing
-
In conjunction with the Operations Team, monitor the network's
performance.
-
Monitor and deal with users' requests in the light of the restricted
network.
-
Prepare an inventory of all communications equipment requiring
replacement in order for the original computer processing
environment to be re utilised.
-
Order replacement equipment as required (in conjunction with the
Disaster Management Team for. expenditure approval).
6.5.Facilities Team Tasks
6.5.1.Immediate
-
Provide an initial damage report to the Disaster Management Team
Leader.
-
Alert and mobilize all other team members.
-
Attend the initial meeting called for recovery team leaders.
6.5.2.Within Three Hours
-
Conduct an asset inventory.
-
Make a full evaluation of the damage.
-
In conjunction with the Operations Team identify all potentially
salvageable equipment.
-
Carry out safety inspections.
-
Make the site secure, to prevent unauthorised access by staff or the
public.
-
Estimate the time required to recover.
-
Report back at the second meeting of recovery team leaders.
6.5.3.Within Twenty Four Hours
-
Provide the required facilities at the Command Centre.
-
Arrange hotel or other temporary accommodation for staff.
-
Set up transport arrangements to/from all temporary locations.
-
Set up an Administration Support Desk to handle all queries.
-
Transfer staff to temporary locations.
-
Remove vital documents from disaster site.
-
Remove re usable equipment from disaster site.
6.5.4.Ongoing
-
Set up administrative support services:
-
Remove salvaged items from the disaster area.
-
Set up security procedures at the standby facility.
-
Contact suppliers of essential services (electricity, gas, water)
and make any arrangements required as a result of the disruption.
-
Supervise delivery and installations at the standby facility.
-
Monitor the installation of:
-
electricity
-
heating/lighting
-
air conditioning
-
fire detection systems
-
access control systems
-
telephones.
if these need to be provided at the standby facility.
-
Provide office furniture for the standby facility if required.
-
In conjunction with the Operations Team, transfer tapes, discs,
documentation, stationery from off site store to standby
facility.
6.6.Communications Team Tasks
Hint:
be sure that the Communications Team has a clear understanding of its
own role and that of the other teams, to ensure no duplication of
effort and/or issuing of conflicting information.
6.6.1.Immediate
Alert and mobilize all other team members.
Attend the initial meeting called for the recovery team leaders.
Set up the Crisis Desk to handle all communications.
6.6.2.Within Three Hours
-
Liaise with the Management Disaster team to agree on the information
to be communicated.
-
If applicable, make initial calls to suppliers of the following and
inform them of the disruption and the likely demands to be made on
their time and services:
-
If applicable, make calls to customers and inform them of any
potential delays.
-
If applicable, issue a statement to local, national and
international Press, as appropriate.
6.6.3.Within Twenty Four Hours
-
Advise all user departments of the transition plans and the
arrangements during the period prior to the actual transition.
6.6.4.Ongoing
-
Handle all public relations.
6.7.<Other Recovery Teams> Tasks
Hint: Repeat this section for all the other recovery teams
which are part of your solution.
6.7.1.Immediate
6.7.2.Within Three Hours
6.7.3.Within Twenty-Four Hours
6.7.4.Ongoing
7.The Command Centre
This section describes the Command Centre, from where the Disaster
Management Team will direct disaster recovery operations.
7.1.Primary Command Centre
If the <Company Name> premises at <Company Address> are
intact following the disaster, the command centre will be located
at:
<Location of primary command centre>.
7.2.Alternative Command Centre
If an alternative command centre is necessary, the command centre
will be located at:
<Location of alternative command centre>.
7.3.Command Centre Requirements
The following command centre resources are required, and will be
supplied by the team indicated.
Hint: This is not intended to be a definitive list, but may
contain a few suggestions which you find helpful.
-
Item:
|
To be
supplied by team:
|
Disaster
recovery Plan
|
|
Whiteboard /
flip chart & stand
|
|
Petty Cash
|
|
Computer Users
Year Book
|
|
Telecom
telephone directory
|
|
Desks, chairs
|
Facilities
|
< >
telephone lines
|
Networks
|
< >
dedicated lines
|
|
Mobile phones
|
Networks
|
Fax machine
|
Facilities
|
Photocopier
|
Facilities
|
Shredder
|
Facilities
|
Tool kit (cables
and plugs)
|
Facilities
|
Office supplies
|
Facilities
|
Refreshments
(coffee, tea and so on)
|
Facilities
|
Camp beds
|
Facilities
|
Shower facility
|
Facilities
|
Car parking
|
Facilities
|
First aid kit
|
Facilities
|
Refrigerator
|
Facilities
|
Microwave oven
|
Facilities
|
8.The Standby Facility
Hint: state if the Standby Facility is for computer processing
only, or whether it also provides some office space. If you use an
external Company to provide this facility, you may find standard
information supplied to enable you to use the service will fit well
into this section.
This section provides a general introduction to the standby facility
which the <Company Name> can utilise for computer processing
<and office space> following a disaster.
It provides detailed information on preparing the facility.
This information includes the following:
8.1.Location of the Standby Facility
The address of the Standby Facility is:
Instructions on how to get to the Standby Facility are as follows:
8.2.Standby Alert Confirmation Sheet
Hint: Where standby facilities are provided by a vendor on a
commercial basis, the vendor may require written confirmation of
the invocation of the service. Therefore be prepared to provide
typically the following details.
The following form is used to confirm the invocation of the Standby
Facilities. It must be completed by the Disaster Management Team
Leader and communicated to the Standby Facility Vendor at
<Vendor address, fax number, phone number>.
-
Company Name:
|
|
Address:
|
|
Telephone Number:
|
|
Disaster Alert
Agreement Number:
|
|
Designated Site:
|
|
Nature of Disaster:
|
|
Estimated Duration of Usage of the Standby Facility:
|
|
Date Usage to Start:
|
|
Name:
|
|
Signature:
|
|
Date:
|
|
9.The Data Storage Location(s)
This section describes the location(s) of the vault facilities where
secure copies of data backups and other vital information are
stored.
9.1.Storage Location 1
-
Location and address:
|
|
Contact person:
|
|
Contact phone number:
|
|
Number of vault/safe:
|
|
Type of vault/safe:
|
|
Maximum capacity:
|
|
Content:
|
|
9.2.Storage Location 2
-
Location and address:
|
|
Contact person:
|
|
Contact phone number:
|
|
Number of vault/safe:
|
|
Type of vault/safe:
|
|
Maximum capacity:
|
|
Content:
|
|
10.Critical Business Lessons
Hint: The Class 1 applications correspond to the ‘must have’
and the Class 2 to the ‘want’ applications as defined in the
Business Impact Assessment.
This section describes the system requirements for <Company
Name>’s critical business applications in the Standby Facility.
It is divided into two sections: Class 1 systems (“must-have”)
and Class 2 systems (important), with the timescales for these
systems to support the business.
Refer to Section 12.4, User Groups and Application Support, for the
names of the application owner.
10.1.Class 1 Systems
-
Timescale
|
Application
|
System Requirements (Hardware, Software, Communications, Data,
Documentation)
|
Number of Users
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10.2.Class 2 Systems
-
Timescale
|
Application
|
System
Requirements (Hardware, Software, Communications, Data,
Documentation)
|
Number
of Users
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11.Supplies for the Standby Facility
This section contains checklists of all supplies, documentation and
equipment you need to obtain for the Standby Facility for business
survival (such as billing stationery). It lists what you need and where
to obtain it.
Hint: again, you are reminded that these are not
recommendations and you should decide and note here what is appropriate
to your needs.
11.1.Supplies
Supplies required are as follows:
-
Item
|
Location/Vendor
|
Comments (e.g.
duration of stock, supplier response time)
|
|
|
|
|
|
|
|
|
|
|
|
|
11.2.Documentation
The Systems documentation required is as follows:
-
Item
|
Location/Vendor
|
Comments
|
System
Specifications
|
|
|
Program
Specifications
|
|
|
File
Specifications
|
|
|
Record
Specifications
|
|
|
Support Manuals
|
|
|
The Operations documentation required is as follows:
-
Item
|
Location/Vendor
|
Comments
|
Operations
Standards And Procedures
|
|
|
Operations
Manuals
|
|
|
Run Instructions
|
|
|
Job Control
Sheets
|
|
|
Sample Input
Documents
|
|
|
Networks
Documentation
|
|
|
11.3.Other Equipment
Other equipment required is as follows:
-
Item
|
Location/Vendor
|
Comments
|
|
|
|
|
|
|
|
|
|
|
|
|
12.Directories
Hint: The information in this section may often be stored and
maintained in a database tool. If so, this section will include printed
reports obtained from the software.
This section of the plan contains a series of directories.
These directories contain the type of information which is most
likely to change such as names, addresses, telephone numbers etc.
It is important to keep these directories up to date.
12.1.Emergency Services
-
Service
|
Phone
|
Address
|
Police
|
|
|
Fire
|
|
|
Hospitals
|
|
|
Gas
|
|
|
Gas Escapes (24
hours)
|
|
|
Electricity
|
|
|
Electricity
Supply Enquiries (24 hours)
|
|
|
Water
|
|
|
Burst Pipes/ Emergencies (24 hour)
|
|
|
12.2.Recovery Team Members
There are <> recovery teams.
The staffing of these Recovery Teams is listed in this section. The
team leader is the first name in the list, in the shaded box.
12.2.1.Disaster Management Team: Members and Contacts
-
Name
|
Work Phone
|
Home Phone
|
Pager/other
contact info
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.2.2.Operations Team: Members and Contacts
-
Name
|
Work Phone
|
Home Phone
|
Pager/other
contact info
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.2.3.Networks Team: Members and Contacts
-
Name
|
Work Phone
|
Home Phone
|
Pager/other
contact info
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.2.4.Facilities Team: Members and Contacts
-
Name
|
Work Phone
|
Home Phone
|
Pager/other
contact info
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.2.5.Communications Team: Members and Contacts
-
Name
|
Work Phone
|
Home Phone
|
Pager/other
contact info
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
12.3.First Aiders
For First Aid during office hours, contact <Name> at
<Contact Number>.
If a first aider is not immediately available, contact the Emergency
ambulance service by dialling <emergency service telephone
number>.
12.4.User Groups and Application Support
Hint: This table lists the users who can provide support for
each application. Ensure that there is a user contact listed for each
critical business application that is defined in Section 10, Critical
Business Applications.
-
System/Application
|
Contact
|
Phone
|
|
|
|
|
|
|
|
|
|
12.5.Vendor and Supplier Contacts
This section lists all the key vendors and suppliers who need to be
contacted following a disaster.
Hint: Adapt this list as necessary.
-
Requirement
|
Contact/
Company
|
Phone /Fax
(working hours)
|
Phone outside
working hours
|
Contract no.
if any
|
Field Service
|
|
|
|
|
Hardware
|
|
|
|
|
Data
communications
|
|
|
|
|
Voice
communications
|
|
|
|
|
Wide Area Network
Equipment
|
|
|
|
|
Software
|
|
|
|
|
Magnetic Media
|
|
|
|
|
Office Equipment
|
|
|
|
|
Furniture
|
|
|
|
|
Banking
|
|
|
|
|
Air Conditioning
|
|
|
|
|
Fire Protection/
Detection
|
|
|
|
|
Computer Room
Cleaning
|
|
|
|
|
Disc Pack
Cleaning/ Checking
|
|
|
|
|
Decollator/
Guillotine Service
|
|
|
|
|
Fire Safe
Maintenance
|
|
|
|
|
Salvage
Contracting Services
|
|
|
|
|
Transport
(Car/Truck hire)
|
|
|
|
|
Courier Services
|
|
|
|
|
Portable office
buildings
|
|
|
|
|
Stationery
|
|
|
|
|
13.Inventories
Hint: The information in this section may be stored and
maintained in a database or other type of software tool. If so, this
section may include printed reports obtained from the software. Many
Organisations will have this information recorded as an Asset Register.
You may wish to include the Asset Number assigned to any item. Keeping
this information accurate will help with administration of any Insurance
claims.
This section contains inventories of all computer hardware, software
and other equipment.
13.1.Computer Hardware
-
Manufacturer
|
Model,
Description, Number
|
Qty
|
|
Mainframes/Processors/Servers
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Workstations
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PCs
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Disk drives
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tape drives
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Printers
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Network
equipment
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Hint: The tables below are in an alternative, more complete
format for listing the hardware inventory. Duplicate the table as
necessary.
-
MAINFRAMES/SERVERS
|
Identifier
such as Scary
|
Sporty
|
Ginger etc.
|
Manufacturer
|
|
|
|
Model,
Description, Number, Code
|
|
|
|
Capital Value as
Asset
|
|
|
|
Rental Cost
|
|
|
|
Capital Value for
Insurance
|
|
|
|
Maintenance
Contract Number
|
|
|
|
Contract Expiry
Date
|
|
|
|
Rental Contract
No.
|
|
|
|
Location,
Department
|
|
|
|
Supply Date
|
|
|
|
|
|
|
|
WORKSTATIONS
|
Identifier
|
Identifier
|
Identifier
|
Manufacturer
|
|
|
|
Model,
Description, Number, Code
|
|
|
|
Capital Value as
Asset
|
|
|
|
Rental Cost
|
|
|
|
Capital Value for
Insurance
|
|
|
|
Maintenance
Contract Number
|
|
|
|
Contract Expiry
Date
|
|
|
|
Rental Contract
No.
|
|
|
|
Location,
Department
|
|
|
|
Supply Date
|
|
|
|
|
|
|
|
-
PCs
|
Family Type 1
|
Family Type 2
|
Family Type 3
|
Manufacturer
|
|
|
|
Model,
Description, Number, Code
|
|
|
|
Capital Value as
Asset
|
|
|
|
Rental Cost
|
|
|
|
Capital Value
for Insurance
|
|
|
|
Maintenance
Contract Number
|
|
|
|
Contract Expiry
Date
|
|
|
|
Rental Contract
No.
|
|
|
|
Location,
Department
|
|
|
|
Supply Date
|
|
|
|
Quantity
|
|
|
|
-
DISK DRIVES
|
Family Type 1
|
Family Type 2
|
Family Type 3
|
Manufacturer
|
|
|
|
Model,
Description, Number, Code
|
|
|
|
Capital Value as
Asset
|
|
|
|
Rental Cost
|
|
|
|
Capital Value
for Insurance
|
|
|
|
Maintenance
Contract Number
|
|
|
|
Contract Expiry
Date
|
|
|
|
Rental Contract
No.
|
|
|
|
Location,
Department
|
|
|
|
Supply Date
|
|
|
|
Quantity
|
|
|
|
-
TAPE DRIVES
|
Family Type 1
|
Family Type 2
|
Family Type 3
|
Manufacturer
|
|
|
|
Model,
Description, Number, Code
|
|
|
|
Capital Value as
Asset
|
|
|
|
Rental Cost
|
|
|
|
Capital Value
for Insurance
|
|
|
|
Maintenance
Contract Number
|
|
|
|
Contract Expiry
Date
|
|
|
|
Rental Contract
No.
|
|
|
|
Location,
Department
|
|
|
|
Supply Date
|
|
|
|
Quantity
|
|
|
|
-
PRINTERS
|
Family Type 1
|
Family Type 2
|
Family Type 3
|
Manufacturer
|
|
|
|
Model,
Description, Number, Code
|
|
|
|
Capital Value as
Asset
|
|
|
|
Rental Cost
|
|
|
|
Capital Value
for Insurance
|
|
|
|
Maintenance
Contract Number
|
|
|
|
Contract Expiry
Date
|
|
|
|
Rental Contract
No.
|
|
|
|
Location,
Department
|
|
|
|
Supply Date
|
|
|
|
Quantity
|
|
|
|
-
NETWORK
EQUIPMENT
|
Item 1
|
Item 2
|
Item 3
|
Manufacturer
|
|
|
|
Model,
Description, Number, Code
|
|
|
|
Capital Value as
Asset
|
|
|
|
Rental Cost
|
|
|
|
Capital Value
for Insurance
|
|
|
|
Maintenance
Contract Number
|
|
|
|
Contract Expiry
Date
|
|
|
|
Rental Contract
No.
|
|
|
|
Location,
Department
|
|
|
|
Supply Date
|
|
|
|
|
|
|
|
13.2.Non-computer Equipment
Device
|
Model,
Description, Number
|
Quantity
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.3.Software Inventory
Supplier
|
Name, Version,
etc.
|
Qty
|
License no.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
13.4.Operating Systems
Manufacturer
|
Name of Operating System, Version
|
No of licences
|
|
|
|
|
|
|
14.Related Documentation
This section contains references to other key documentation which
must be copied and kept in the vault location, together with < >
copies of this Disaster recovery Plan.
Hint: for example:
The reference documentation includes:
-
Data backup procedures
-
Type(s) of backups
-
Means of identification
-
Length of time that backups are kept
-
Frequency of backups
-
Times when backups are performed
-
Method of rotating sets of backups
-
Emergency procedures
-
Fire
-
Bomb
-
Flood
-
Power Failure
-
Evacuation
-
First Aid
|