p590 Microcode Upgrade procedures Scheduled for 06/03/2006

The following document describes the procedure to upgrade the Microcode on the MX1 IBM p590 systems scheduled to occur on June 3, 2006. Upgrading the microcode requires the each frame in the pair to be powered-down, causing all systems running on the frame to be shutdown. Since production databases are running on each frame, a microcode upgrade requires the coordination of the AIX system administration team, DBA's, and application administrators.

    Summary of Activities

  1. The first phase of this process is to upgrade the HMC associated with the p590 frames.
  2. Then failover all production systems to the alternate frame. Non-production systems will not be failed over, they will simply be shutdown.
  3. Next, power off the p590 frame and perform the Microcode upgrade.
  4. After microcode upgrade is complete and verified, power up the p590 and restart all systems.
  5. Failback all production systems and test.
  6. Repeat this process for the second p590 frame.




Phase 1

- Upgrade the HMC associated with the MX1 p590 frames.


Phase 1 Start Time:
Phase 1 Duration:


Phase 2

- System Failovers

Failover all production systems to the alternate frame. Non-production systems will not be failed over, they will simply be shutdown.


Phase 2 Start Time:
Phase 2 Duration:



Phase 3

- Perform Microcode upgrade on frame 9119-590-SN51A972E


Phase 3 Start Time:
Phase 3 Duration:



Phase 4

- Power on p590 Frame 9119-590-SN51A972E and activate systems


Phase 4 Start Time:
Phase 4 Duration:



Phase 5

- Application Failback

Failback the production databases and production application servers.


Phase 5 Start Time:
Phase 5 Duration:



Phase 6

- Power on p590 Frame 9119-590-SN51A973E and activate systems


Phase 4 Start Time:
Phase 4 Duration:



Phase 7

- Application Failback

Failback the production databases and production application servers to the second frame.


Phase 7 Start Time:
Phase 7 Duration:



Phase 8

- Project Completion

Notify all interested parties of project completion.


Phase 8 Start Time:
Phase 8 Duration: