This section is for Base Build Documents. Here you will find simple instructions to install a server. This is also where you will find the basic, common requirements for a given server and platform to build a server from scratch. Another notable item included within this section is "common customization" of servers. This is a list of specific items that are common to all servers that are not a base build but common to the TXU AIX build for all environments and applications. Detail How-To documents to explain these processes are located HERE

To add anything to this section, contact Joseph Stephens.





Common Build Checklist

1.) Configure Server in HMC if P4/5-LPAR ( Hardware Management Console )

2.) Install Server via NIM ( either mdcnim or ddcnim - depending on the Datacenter the target Server resides in )

3.) NIM install via mksysb for existing configurations ( e.g. adding an eGate Server will use the eGate mksysb )

4.) NIM install via base media for new configurations ( Create mksysb for this configurations for future installs )

5.) Configure SNMP ( integrate "xmpeek -l hostname" into all systems startup procedure )

6.) Configure TSM ( Standard and HACMP configurations )

7.) Configure TEC ( Standard and HACMP configurations )

8.) Configure TXUpro ( ProWeb )

9.) Configure NMON ( Performance reporting )

10.) Add Server to CMDB ( Configuration Management Database )

11.) Set ODM Error Notify ( Notification to TEC when hardware errors are detected )

12.) Create XMON User ( user id for performance based administrative logins )

13.) Tune Memory on System ( vmtune install )

14.) Install and run invscout ( inventory management for patch and microcode revisions )

15.) Tune TCP/IP ( disable IPv6, tune specific TCP Stack components )

16.) Install DocitWeb ( Hardware and OS inventory of systems )

17.) Tune NFS ( only if server uses nfs )

18.) Install Performance Toolbox ( Client and Server binaries - configure to be seen by PerfToolbox Server )

19.) Install INQ utility ( information tool for drives )

20.) Install KSH93.att ( Install latest KSH for compatibility with existing scripts and programs )

21.) Install SUDO ( Administrative/Security Tool )

22.) Install SSH ( Administrative/Security Tool )

23.) Validate System Components ( Rootvg filesystem sizes, paging space size and placement, etc ... )

24.) Validate PCI Card Slot Placement ( NIC, SCSI, SSA, GigE, etc ... )

25.) Set SSH Keys for xmon user to eperf ( for administrative activities and existing programs to work )

26.) Configure Rshell passwordless login to NIM Servers ( For NIM functionality and DR functionality )

27.) Set System Dump Space to hd7x and hd7y ( System Dump Space )

28.) Set Paging Space up on seperate spindle ( hd6 on seperate disk if large enough and seperate VG for additional paging space )

29.) Update Frame/System Spreadsheet ( Publish updated spreadsheet to Eperf )

30.) Validate LUN List ( SAN disks are presented correctly, HDLM Setup and rootvg and pagingvg in exclusion list for HDLM )

31.) Configure NTP ( Configure Time daemon )

32.) Configure Prompt ( Configure PS1 in /etc/profile )

33.) Configure MOTD ( Configure MOTD in /etc/motd )

34.) Configure Herald ( Configure Herald in /etc/security/login.cfg )

35.) Configure Base User Security ( Configure defaults i.e. password limits )

36.) Configure Server in PLM if P5-LPAR ( Partition Load Manager )

37.) Remove Rshell passwordless login to NIM Servers ( Upon Build completion and pior to turnover )

38.) Configure Server for Secure Access Portal ( Upon Build Completion Portal not complete yet )

39.) Generate New Secure Root Password ( Generate Password and deliver to Unix Team Lead )

40.) Create Change Ticket for LOS Turnover ( LOS Manager and Team Lead as approvers )



New system build task list assembled for virtualization follows:



System Build Tasks - Detailed Function List

Facilities Preparation

Node Names / IP Addresses / DNS Host Names

9h45m

HMC Preparation

26h30m

NIM Server Preparation

16h30m

Frame Preparation

25h0m

VIO Server LPAR Preparation

24h30m

VIO Client LPAR Preparation

24h45m

VIO Server Build

42h0m

VIO Client LPAR Build

75h0m

High Availability Clustered Multi-Processing

95h15m

Disaster Recovery

283h15m

Configuration Management

Change Management

Availability Management

Incident Management

Problem Management

Outage Management

Project Management